Project financed by the Norwegian Grants 2009 - 2014, within the RO 19 - Public Health Initiative.
The project “Improving the Health Status of the Romanian Population by Increasing Tuberculosis Control” began a 7 August 2014 and aims at strengthening the tuberculosis (TB) control in Romania, with focus on multidrug resistant tuberculosis (TB) in Romania, with focus on multidrug resistant tuberculosis and extensively resistant TB (MDR/XDR TB) and poor and vulnerable groups.
Following the additional, on 4 December 2014 the additional agreement was signed for the extension of the project, it value becoming 10 740 280 EURO.
Thus, the operational objectives of the project were also extended, from 4, the initial number, to 8 objectives at the time being:
At this moment, there are 13 work packages under development, comprising activities meant to increase the TB control level in Romania and the awareness degree of the public regarding this affection.
The funds necessary for the project implementation for August-December 2014 were transferred in November 2014, that is after 4 months after the beginning of the project. Nonetheless, at the end of December 2014, 91% of the funds were spent for ensuring drugs for 750 patients.
After almost 5 months after the beginning of the project, in 31 December 2014, all the activities are according o the established schedule, and the most important results obtained are the following:
The total budget of the project is 10 748 280 Euro, respectively 47 308 554.42 RON.
In November and December, the Ministry of Health transfer to the “Marius Nasta” Institute the amount representing the advance of 25%, respectively 11 827 137.50 lei. Until the end of December, 10 300 541.02 lei were spent, representing 87% of the transferred funds. Of the total funds spent, more than 91% were spent for ensuring the treatment of patients with MDR/XDR B.
The spending for the period 1 August – 31 December 2014 are shown in the table below:
|
No. |
BUDGET LINE |
Total spent value |
|
|
1 |
Human Resources |
809,424.42 |
|
|
2 |
Transportation costs for staff and volunteers |
0.00 |
|
|
3 |
Supplies |
9,441,021.86 |
|
|
4 |
Costs for investments (with the maximum limit set for each call of projects) |
0.00 |
|
|
5 |
Other costs related to the service provision towards beneficiaries |
13,908.28 |
|
|
6 |
Communication and promotion of the project |
0.00 |
|
|
7 |
Bilateral activities |
0.00 |
|
|
8 |
Other subcontracted activities |
714.24 |
|
|
9 |
Indirect costs |
35,472.22 |
|
|
10 |
Unexpected costs |
0.00 |
|
|
Total |
10,300,541.02 |
||